
The most common ADU timeline question is "how long until we can rent it out?" The honest answer is 9–14 months for a detached new-construction ADU in the Bay Area — and the construction phase isn't usually the bottleneck. Here's the realistic month-by-month breakdown.
Phase 1 — Design and engineering (8–14 weeks)
- Initial site visit and feasibility (1 week)
- Schematic design and selection (3–4 weeks)
- Construction drawings (3–5 weeks)
- Structural engineering (concurrent, 2–3 weeks)
- Title 24 energy calcs (1–2 weeks)
If your city requires a soils report (most Bay Area cities do for new construction), add 2–3 weeks. Hillside lots can add another 2–4 weeks for additional geotechnical work.
Phase 2 — Permits (8–16 weeks)
This is where ADU timelines surprise homeowners. Even with the state's ADU streamlining laws:
- First plan check round: 4–8 weeks (varies by city)
- Revisions and resubmittal: 2–4 weeks
- Second plan check round: 2–4 weeks
- Permit issuance: 1–2 weeks
Cities like San Mateo, Mountain View, and Sunnyvale tend to be faster. Palo Alto, San Francisco, and Burlingame's design review districts run slower.
Phase 3 — Construction (varies by ADU type)
Detached new-construction (5–7 months)
- Site prep and foundation: 4–5 weeks
- Framing and sheathing: 3–4 weeks
- MEP rough-in: 3–4 weeks
- Insulation, drywall, exterior: 4–5 weeks
- Finishes (cabinets, tile, flooring, paint): 6–8 weeks
- Final inspections and certificate of occupancy: 1–2 weeks
Attached ADU / addition (4–6 months)
Slightly faster than detached because you skip some site work, but the tie-in to the existing structure can introduce surprises.
Garage conversion (3–4 months)
- Slab evaluation and prep: 1 week
- Framing modifications (egress windows, interior walls): 2–3 weeks
- MEP rough-in: 2–3 weeks
- Insulation, drywall: 2 weeks
- Finishes: 4–6 weeks
- Inspections: 1 week
What can extend the timeline
- Utility upgrades. If PG&E needs to upgrade your service, that's their schedule, not yours. Allow 2–6 months.
- Sewer lateral. Some cities require sewer lateral replacement when an ADU is added. Add 2–4 weeks.
- Tree protection. If your site has protected trees, plan reviews can add 4–8 weeks.
- Material lead times. Custom cabinets and certain windows can be 12–16 weeks out.
What can compress it
- Pre-approved ADU plans (offered by some cities, cuts plan check)
- Standardized cabinet packages instead of custom
- Garage conversion path (skips foundation + framing)
- Working with a design-build contractor (parallel design + permits + construction prep)
See a recent ADU we completed in San Mateo, or learn more about our ADU construction services.
Planning a Bay Area remodel?
High Touch Consulting & Development is a licensed general contractor serving the San Francisco Peninsula and Silicon Valley. We provide free on-site consultations and fixed-scope written proposals.


